E Cube

Energy | Efficiency | Environment

  • Home
  • About
    • Clients
    • Story
    • People
    • Approach
    • News
  • Services
    • New Building Commissioning
    • IECC Commissioning
    • Retro-Commissioning
    • LEED Services
    • Fault Detection & Diagnostics
    • Existing Building Optimization
    • Building Enclosure Commissioning
    • Measurement & Verification
    • Energy Benchmarking
    • Troubleshooting
    • Due Diligence
    • Contractor Support
    • Sustainable Design Programs
    • Utility Programs
  • Projects
    • Healthcare
    • Higher Education
    • K-12
    • Hospitality
    • Laboratories
    • Data Centers
    • Commercial Office
    • Governmental
    • Aviation
    • Central Plants
  • Contact

Google – Chicago Offices

Location: Chicago, IL
Project Floor Area: 62,000 sf
Project Cost: $7.4 Million
Completion: Mar 2014
LEED Rating: Silver
Project Manager: Mandeep Singh

E Cube led commissioning efforts for Google’s office build-outs at 20 W. Kinzie. This consisted of 3 separate projects on various floors of the facility. The efforts incorporated interfacing with landlord staff to ensure proper operation of the tenant MEP systems and training.

E Cube provided LEED design phase and construction phase commissioning services in the interest of achieving the Fundamental Cx Prerequisite and Enhanced Commissioning Credit. For the construction phase, E Cube led a comprehensive, multi-stage commissioning process for the mechanical (HVAC), building automation, lighting controls, and plumbing systems.

E Cube provided LEED Fundamental and Enhanced Commissioning services for these projects.

Key E Cube Services for this project

  • Owner’s Project Requirement and Basis of Design
  • Design assistance review at the DD and CD phases
  • Commissioning documents including: Cx Spec, Cx Plan
  • Pre-functional equipment and systems documentation
  • Oversight of contractor pre-startup testing, startup and TAB procedures
  • Subsystem and system functional performance testing
  • Review of Operation and Maintenance Manuals
  • Review of Operation and Maintenance Training
  • Commissioning Report & Systems Manual
  • Warranty Phase follow-up review